A, B and C can complete a work
in 20, 24 and 30 days respec-
tively. All three of them start
together but after 4 days A left
the job and B left the job 6 days
before the work was complet-
ed. C completed the remaining
work alone. In how many days
was the total work completed?

How to solve like these questions

Replies to this post

P
Praveen
1
P
pavan

14 days

1
R
Rajesh

14 days